Construction Update Archive
Previous schedule of activities:
Week of June 19th
New Windsor
No major activities planned
Hamptonburgh
No major activities planned
Blooming Grove
No major activities planned
Chester
Grading and drainage work at Sugarloaf Substation
Continue right of way restoration
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Minor activities at 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of June 12th
New Windsor
No major activities planned
Hamptonburgh
No major activities planned
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Restoration activities beginning on the project right of way
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Minor activities at 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of June 5th
New Windsor
No major activities planned
Hamptonburgh
No major activities planned
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Continue removing equipment from 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of May 29th, 2023 (No Work on May 29th)
New Windsor
No major activities planned
Hamptonburgh
No major activities planned
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Continue removing equipment from 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of May 22nd, 2023
New Windsor
Restoration activities occuring
Hamptonburgh
No major activities planned
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Continue removing equipment from 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of May 15th, 2023
New Windsor
Continue restoration activities
Hamptonburgh
Continue restoration activities
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Finish activities at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Continue removing equipment from 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of May 8th, 2023
New Windsor
Continue restoration activities
Hamptonburgh
Continue restoration activities
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Finish activities at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Start removing equipment from 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of May 1st, 2023
New Windsor
Continue restoration activities
Hamptonburgh
Continue restoration activities
Blooming Grove
Continue restoration activities
Chester
Grading and drainage work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Complete restoration activities at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Start removing equipment from 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of April 24th, 2023
New Windsor
Continue restoration activities
Hamptonburgh
Continue restoration activities
Blooming Grove
Continue restoration activities
Chester
Conduit and cable work at Sugarloaf Substation
Fence installation at Sugarloaf Substation site
Testing activities at the Sugarloaf Substation site
Complete testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of April 17th, 2023
New Windsor
Continue restoration activities
Conductor and fiber optic wire installation outside the Rock Tavern Substation
Hamptonburgh
Continue restoration activities
Finalize equipment on installed structures
Blooming Grove
Begin restoration activities
Finalize equipment on installed structures
Chester
Clip conductor to structures between Booth Road and the Sugarloaf Substation
Grounding work at Sugarloaf Substation site
Complete retaining wall installation
Fence installation at Sugarloaf Substation site
Fiber optic testing at the Sugarloaf Substation site
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of April 10th, 2023
New Windsor
Continue restoration activities
Hamptonburgh
Continue restoration activities
Blooming Grove
Continue restoration activities
Finalize equipment on installed structures
Chester
Install transmission line conductor and fiber optic cable
Sag wires between Booth Road and the Sugarloaf Substation
Grounding work at Sugarloaf Substation site
Install retaining wall at Sugarloaf Substation
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Continue using Route 208 site for matting and access equipment.
Week of April 3rd, 2023
New Windsor
Continue restoration activities
Finalize equipment on installed structures
Hamptonburgh
Continue restoration activities
Finalize equipment on installed structures
Blooming Grove
Begin restoration activities
Finalize equipment on installed structures
Chester
Install transmission line conductor and fiber optic cable
Sag wires between Booth Road and the Sugarloaf Substation
Grounding work at Sugarloaf Substation site
Fence installation at Sugarloaf Substation site
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Removing materials from Route 208 laydown yard. Begin using site for matting and access equipment.
Week of March 27th, 2023
New Windsor
Begin restoration activities
Finalize equipment on installed structures
Hamptonburgh
Begin restoration activities
Finalize equipment on installed structures
Blooming Grove
Finalize equipment on installed structures
Chester
Set steel structures outside Sugarloaf Substation
Sagging and clipping new conductor to transmission structures
Grounding work at Sugarloaf Substation site
Fence installation at Sugarloaf Substation site
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Removing materials from Route 208 laydown yard. Begin using site for matting and access equipment.
Week of March 20th, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
Clipping and sagging of conductor a between Prospect Road and the Town of Chester
Chester
Sagging and clipping new conductor to transmission structures
Grounding work at Sugarloaf Substation site
Fence installation at Sugarloaf Substation site
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Removing materials from Route 208 laydown yard. Begin using site for matting and access equipment.
Week of March 13th, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
helicopter operations between Prospect Road and the Town of Chester
Chester
helicopter work to install new conductor on transmission structures
Grounding work at Sugarloaf Substation site
Fence installation at Sugarloaf Substation site
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Removing materials from Route 208 laydown yard. Begin using site for matting and access equipment.
Week of March 6th, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
Wire stringing via helicopter
Prepare structures for wire stringing
Complete setting structures
Chester
Sagging and clipping new conductor to transmission structures
Transformer assembly at the new 115kV Sugarloaf Substation
Grounding work at Sugarloaf Substation
Prepare for fence installation at Sugarloaf Substation
Retaining wall installation at Sugarloaf Substation
Testing activities at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Removing materials from Route 208 laydown yard.
Week of February 27th, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
Complete clipping and sagging north of Prospect Road
Prepare for clipping and sagging south of Prospect Road
Structure installations south of Bull Mine Road
Chester
Structure Installations
Structural steel installation scheduled for completion at the Sugarloaf Substation site
Foundation installations near Sugarloaf Mountain Road
Grounding work at Sugarloaf substation site
Testing of equipment at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Removing materials from Route 208 Laydown yard
Week of February 20, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
Structure installation near Farmingdale Road
Conductor and optical ground wire installation between Tuthill Road and Prospect Road
Steel structure installation south of Prospect Road
Chester
Foundation and structure installation near Booth Road, Laroe Road, and Sugarloaf Mountain Road
Sugarloaf Substation Autotransformer assembly, and oil processing
Structural steel will be installed at the substation site
Grounding work at substation site
Equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of February 13, 2023
New Windsor
Sag and clip conductor
Hamptonburgh
Sag and clip conductor
Blooming Grove
Foundation installation in locations near Old Mansion Road
Install structure near Prospect Road
Sag and clip conductor
Chester
Foundation and structure installation near Booth Road and Laroe Road
Sugarloaf Substation autotransformer delivery, assembly, and oil processing
Structural steel and H-frame structure will be installed at the Sugarloaf Substation site
Control building assembly at Sugarloaf Substation
Begin substation retaining wall installation
Equipment installations including wire and grounding at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of February 6, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
Foundation installation in locations near Old Mansion Road
Structure installation near Farmingdale Road
Sag and clip conductor
Chester
Foundation and structure installation near Laroe Road and Sugarloaf Mountain Road
Structural steel will be installed at the substation site
Control building assembly at Sugarloaf Substation
Equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Ground grid and ground well installations at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown YardWeek of January 30, 2023
New Windsor
No major work anticipated
Hamptonburgh
No major work anticipated
Blooming Grove
Foundation installation at locations near Old Mansion Road
Structure installation near Farmingdale Road
String conductor and Optical Ground Wire (OPGW)
Sag and clip conductor
Chester
Foundation and structure installation near Laroe Road and Sugarloaf Mountain Road
Structural steel will be installed at the substation site
Control building assembly at Sugarloaf Substation
Equipment and conduit installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Ground grid and ground well installations at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of January 23, 2023
New Windsor
String conductor and Optical Ground Wire (OPGW)
Sag and clip conductor
Hamptonburgh
String conductor and Optical Ground Wire (OPGW)
Sag and clip conductor
Blooming Grove
Foundation and structure installation at multiple locations
String conductor and Optical Ground Wire (OPGW)
Sag and clip conductor
Chester
Foundation and structure installation at multiple locations
Structural steel will be installed at the new Sugarloaf Substation
Equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Control building assembly at Sugarloaf Substation
Materials receiving at 43 Andrews Lane Laydown Yard
Ground grid and ground well installations at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of January 15, 2023
New Windsor
Helicopter wire stringing
Hamptonburgh
Helicopter wire stringing
Blooming Grove
Helicopter wire stringing
Concrete foundation installation at multiple locations
Structure Installation
Chester
The Sugarloaf Substation pre-fabricated control house is scheduled to be delivered on January 18th
Structural steel will be installed at the substation site
Equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Ground grid and ground well installations at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of January 2, 2023
New Windsor
Setup pulling equipment in right of way
Hamptonburgh
Setup pulling equipment in right of way
Blooming Grove
Structure installation
Concrete foundation installation at multiple locations
Chester
Foundations work for structures off Sugar Loaf Mountain Road
Clearing work in right of way
Equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Ground grid, cable trench and steel staging at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of December 25, 2022
No Work
Week of December 18, 2022
New Windsor
No work
Hamptonburgh
No work
Blooming Grove
Structure installation
Concrete foundation installation
Chester
No Transmission line work
Grounding and equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of December 12, 2022 (Work taking place on Sunday, December 18 north of Prospect Road in Blooming Grove)
New Windsor
No work
Hamptonburgh
No work
Blooming Grove
Structure installation
Concrete foundation installation
Chester
No Transmission line work
Grounding and equipment installations at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of December 5, 2022
New Windsor
No work
Hamptonburgh
No work
Blooming Grove
Structure installation
Concrete foundation installation
Chester
Existing structure demolition and removal
Grounding installations and equipment setting at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of November 28, 2022
New Windsor
No work
Hamptonburgh
Structure installation
Concrete foundation installation
Blooming Grove
Structure installation
Concrete foundation installation
Chester
Existing structure demolition and removal
Grounding installations and equipment setting at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of November 21, 2022 (no work Nov. 23-25)
New Windsor
No work
Hamptonburgh
Structure installation
Concrete foundation installation
Blooming Grove
Concrete foundation installation
Chester
Access road installation
Existing structure demolition and removal
Grounding installations and equipment setting at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of November 14, 2022
New Windsor
Structure installation
Hamptonburgh
Structure installation
Concrete foundation installation
Blooming Grove
Concrete foundation installation
Chester
Existing structure demolition and removal
Above grade grounding work at 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of November 7, 2022
New Windsor
Structure installation
Hamptonburgh
Concrete foundation installation
Blooming Grove
Existing structure demolition and removal
Chester
Access road and pad building
Existing structure demolition and removal
Steel and grounding installations 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Pad building, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of October 31, 2022
New Windsor
Concrete foundation installation
Hamptonburgh
Concrete foundation installation
Blooming Grove
Access road and pad building
Concrete foundation installation
Chester
Access road and pad building
Steel and grounding installations 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of October 24, 2022
New Windsor
Concrete foundation installation
Hamptonburgh
Existing overhead wire and structure demolition and removal
Concrete foundation installation
Blooming Grove
Access road and pad building
Existing overhead wire and structure demolition and removal
Concrete foundation installation
Chester
Access road and pad building
Grounding and stell installations 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of October 17, 2022
New Windsor
Existing overhead wire and structure demolition and removal
Concrete foundation installation
Hamptonburgh
Existing overhead wire and structure demolition and removal
Concrete foundation installation
Blooming Grove
Existing overhead wire and structure demolition and removal
Concrete foundation installation
Chester
Access road and pad building
Steel and grounding installations 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of October 10, 2022
New Windsor
Existing overhead wire and structure demolition and removal
Hamptonburgh
Existing overhead wire and structure demolition and removal
Blooming Grove
Access road and pad building
Existing overhead wire and structure demolition and removal
Chester
Access road and pad building
Steel hauling and grounding installations 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, foundation installations and below grade work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of October 3, 2022
New Windsor
Concrete foundation installation
Hamptonburgh
No work
Blooming Grove
Access road and pad building
Existing overhead wire and structure demolition and removal
Chester
Access road and pad building
Below grade and grounding work at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, and foundation work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and sorting at Route 208 Laydown Yard
Week of September 26, 2022
New Windsor
Existing overhead wire and structure demolition and removal
Concrete foundation installation
Hamptonburgh
Existing overhead wire and structure demolition and removal
Blooming Grove
Access road and pad building
Existing overhead wire and structure demolition and removal
Chester
Concrete foundation installation
Access road and pad building
Below grade and grounding work at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, and foundation work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving, offloading, and sorting at Route 208 Laydown Yard
Week of September 19, 2022
New Windsor
Existing overhead wire and structure demolition and removal
Hamptonburgh
Existing overhead wire and structure demolition and removal
Blooming Grove
Existing overhead wire and structure demolition and removal
Access road and pad building
Chester
Concrete foundation installation
Access road and pad building
Foundation and below grade work at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving and offloading at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal, and foundation work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and foundation reinforcing steel work at Route 208 Laydown Yard
Week of September 12, 2022
New Windsor
Existing overhead wire and structure demolition and removal
Hamptonburgh
Existing overhead wire and structure demolition and removal
Blooming Grove
Access road and pad building throughout the project corridor
Chester
Concrete foundation installation
Foundation work at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal and foundation work at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving and foundation reinforcing steel work at Route 208 Laydown Yard
Week of September 5, 2022
New Windsor
Access road and pad building throughout the project corridor
Hamptonburgh
No work
Blooming Grove
Access road and pad building throughout the project corridor
Chester
Surveying and staking in the project corridor
Concrete foundation installation and curing
Foundation and below grade work at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Materials receiving at 43 Andrews Lane Laydown Yard
Excavation, grading, soil removal and demolition of structure foundations at Sugarloaf 115kV Substation
South Blooming Grove
Materials receiving at Route 208 Laydown Yard
Week of August 29, 2022
New Windsor
No T-Line work
Hamptonburgh
Access road and pad building throughout the project corridor
Blooming Grove
Access road and pad building throughout the project corridor
Chester
Access road and pad building throughout the project corridor
Soil removal and foundation work at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Receiving materials at the 43 Andrews Lane Laydown Yard
Demolition of structure foundations at Sugarloaf 115kV Substation
South Blooming Grove
Receiving materials and concrete work at Route 208 Laydown Yard
Week of August 22, 2022
New Windsor
No T-Line work
Hamptonburgh
Access road and pad building throughout the project corridor
Blooming Grove
Surveying and staking in the project corridor
Access road and pad building throughout the project corridor
Chester
Surveying and staking in the project corridor
Soil removal at the 138kV Sugarloaf Substation off Sugar Loaf Mountain Road
Receiving materials at the 43 Andrews Lane Laydown Yard
Excavation, grading, excess soil removal and demolition of structure foundations at Sugarloaf 115kV Substation
South Blooming Grove
Receiving materials and concrete work at Route 208 Laydown Yard
Week of August 15, 2022
New Windsor
No work
Hamptonburgh
Access road and pad building throughout the project corridor
Blooming Grove
Surveying and staking in the Bull Mill Road area
Access road and pad building throughout the project corridor
Chester
Surveying and staking in the Booth Road and Bull Mill Road areas
Excavation, grading, excess soil removal and demolition of existing structures at Sugarloaf 115kV Substation
Erosion and sediment control installation at the Sugarloaf 138kV Substation
South Blooming Grove
No work
Week of August 8, 2022
New Windsor
No work
Hamptonburgh
Access road and pad building in the Route 208 and Tuthill Road areas
Blooming Grove
Survey work in the Route 17 area
Access road and pad building throughout the project corridor
Chester
Materials delivery at 43 Andrews Lane Laydown Yard
Excavation, grading, excess soil removal and demolition of existing structures at Sugarloaf 115kV Substation
Erosion and sediment control installation at the Sugarloaf 138kV Substation
South Blooming Grove
Steel structures and equipment delivery at Route 208 Laydown Yard
Week of August 1, 2022
New Windsor
No work
Hamptonburgh
Access road and construction workspace installation in the Tuthill Road and Route 208 areas
Blooming Grove
Access road and construction workspace installation in the Tuthill Road and Prospect Road areas
Chester
Material delivery at 43 Andrews Lane Laydown Yard
Erosion control measures at the 138 kV Sugarloaf Substation off Sugar Loaf Mountain Road
Excavation, grading, and demolition of existing equipment at the Sugarloaf 115kV Substation
South Blooming Grove
Delivery of equipment and materials at Route 208 Laydown Yard